Water, Environment, Natural Resources, Tourism and Wildlife Management

Home / Department / Water, Environment, Natural Resources, Tourism and Wildlife Management
Mary Njogu

Mary Njogu

CEC Member for Water, Environment, Natural Resources, Tourism and Wildlife Management
Simon Kemei

Simon Kemei

Chief Officer Water, Environment, Natural Resources, Tourism and Wildlife Management
  • Water

    To increase access to clean and safe water

  • Environmental management and protection

    To protect and conserve the environment

  • Natural resource management

    To sustainably manage and conserve forests

  • Energy

    To increase access to electricity and promote the use of green energy.

NoProject NameProject StatusAmount PaidRemarks
1.Purchase of 6 TippersDelivered and working 69,654,0006 tippers delivered and working
2.Purchase of 2 Fuel TankersDelivered and working 17,306,0002 fuel tankers delivered and working
3.Purchase of 2 Prime moversDelivered and working 31,000,0002 prime movers delivered and working
4.Purchase of 2 Low bedsDelivered and working 8,400,0002 low beds delivered and working
5.Purchase of 4 Long Arm ExcavatorDelivered and working 158,000,0004 long arm excavators delivered and working
6.Purchase of 3 Ordinary ExcavatorDelivered and working 58,950,0003 ordinary excavators delivered and working
7.Purchase of 3 Heavy tracked dozers with ripperAwarded69,300,0003 heavy tracked delivered and working
8.Purchase of 3 BackhoeAwarded0Contract terminated
9.Purchase of 2 Drilling Rig with a test pumping unitDelivered and Working96,343,0002 drilling rigs delivered and working
10.Purchase of 1 Water MasterAwarded and awaiting delivery 0Awaiting ddelivery
11.Purchase of 2 Wheel LoaderAwarded0Contract terminated
12.Drum Rollers, vibratory, self propelled, 10 tonAwarded0Ready for pre-delivery inspection
13.Seiyot Water Project
Borehole Equipping
-Construction of pump house complete
-Construction of borehole chamber complete
-Construction of steel elevated structure done awaiting installation tanks panels.
-Pump installed and tested
-Fencing not complete
0Ongoing
14.Beshebor Water Project
Borehole Equipping
-Construction of pump house complete
-Construction of borehole chamber complete
-Construction of steel elevated structure done awaiting installation tanks panels.
-Pump installation done
-pending fencing
-Needs distribution tank
0Ongoing
15.Chemoset Water project
Borehole Equipping
-Construction of pump house complete
-Construction of borehole chamber complete
-Construction foundation of steel elevated tank complete, steel structure & tank on-going
-Pump installation yet to be done
-Fencing to be done
0Ongoing
16.Kapkures water project
Borehole Equipping
-Construction of pump house complete
-Construction of borehole chamber complete
-Construction foundation of steel elevated tank complete, steel structure & tank on-going
-Solar support structure & accessories complete
-Pump not installed
- Fencing to be done
0Ongoing
17.Ndabarnach water project
Borehole Equipping
-Construction of pump house complete
-Construction of borehole chamber complete
-Construction foundation of steel elevated tank complete, steel structure & tank on-going
-Pump installation complete
-Pending fencing
-School using water (point source)
-Construction of pump house complete
-Construction of borehole chamber complete
-Construction foundation of steel elevated tank complete, steel structure & tank on-going
-Pump installation yet to be done
-Installation of solar panels not done
-Fencing yet to be done
0Ongoing
18.Chepsirya – kapindani water project
Borehole Equipping
-Construction of pump house complete
-Construction of borehole chamber complete
-Construction of steel elevated tank complete
-Installation of solar panels done
-Pump installation complete
-Fencing is complete
1,200m 2” pipeline done
4,993,556.20Complete and operating
19.Chebisaas Sec. water project
Borehole Equipping
-Construction of pump house complete
-Construction of borehole chamber complete
-Installation of solar panels done
-Construction foundation of steel elevated tank complete, steel structure & tank on-going
-Pump installation done
-Fencing not yet done
0Ongoing
20.Kamalel Water Project
Borehole Equipping
-Construction of pump house complete
-Construction of borehole chamber complete
-Pump installation done
4,980,000.00Complete awaiting commissioning of the health facility

-Construction of steel elevated tank done at Kipkenyo complete
21.Lemook Water Project
Borehole Equipping
-Construction of pump house complete
-Construction of borehole chamber complete
-Construction of steel elevated tank complete
-Pump installation complete
4,980,000.00Complete and Operating
22.Aturei Water project
Borehole Equipping
-Construction of pump house complete
-Construction of borehole chamber complete
-Construction of steel elevated tank complete
-Pump installation complete
4,980,000.00Complete and Operating
23.Simat water project
Borehole Equipping
-Construction of pump house complete
-Construction of borehole chamber complete
-Construction of steel elevated tank complete
-Pump installation complete
4,980,000.00Complete and Operating
24.Kisor water project
Borehole Equipping
-Construction of pump house complete
-Construction of borehole chamber complete
-Construction foundation of steel elevated tank tower complete, steel tank structure on-going
-Pump installation complete
0On-going.
25.Kipkenyo dispensary
Borehole Equipping
-Construction of pump house complete
-Construction of borehole chamber complete
-Construction foundation of steel elevated tank tower done, steel tank structure on-going
-Pump installation complete.
Solar panels yet to be installe
0Construction of elevated steel tank and solar panels 0ngoing
26Kamuzee water project
Borehole Equipping
-Construction of pump house complete
-Construction of borehole chamber complete
-Construction foundation of steel elevated tank tower & steel tank structure on-going
-Pump installation complete.
-Solar panels installed
0Elevated steel tank being constructed.
27.Nandi gaa water project
Borehole Equipping
-Construction of pump house complete
-Construction of borehole chamber complete
-Construction foundation of steel elevated tank tower & steel tank structure on-going
-Pump installation complete
Solar panels installed
0Elevated steel tank being constructed.
28.Legebet borehole water project-Construction of pump house complete
-Construction of borehole chamber done
-Construction foundation of steel elevated tank tower done, steel structure works on-going
-Pump installation not yet started
-Fencing done
-Communal water point not done

0On-going
29.Raymoi Borehole water project-Pump house has been done
-Borehole chamber done
-Installation of tower and solar panel
-Fencing done
Elevated steel tank yet to be done
-Solar panels yet to be done
-Pump installation not yet done
-Communal not yet done
0On-going


30.Moiben township Water project-Construction of pump house complete
-Construction of borehole chamber not yet started
-Construction of steel elevated tank done
-Pump installation done
-Solar panels installed
-Fencing done
5,111,705.00Complete and operational
31.Sirikwa Diairies borehole water project-Construction of pump house & fencing complete
-Construction of borehole chamber done
-Construction of steel elevated tank foundation not done
-Pump installation not yet started.
Solar panels not yet installed
0On-going
32.Kaprobu borehole water project-Construction of pump house complete
-Construction of borehole chamber done
-Construction of steel elevated tank complete
-Pump installation done
-Fencing done
-Tower and solar panels installed.
Distribution line to school tank being laid
5,111,705.00Operational
33.Kaptik/Kabomoi Church borehole water project-Construction of pump house complete
-Construction of borehole chamber not done
-Construction of steel elevated tank done
-Pump installation supplied but not installed
-Tower and solar panels installed
-Fencing not done
0On-going
34.Kambi Simba borehole water project-Construction of pump house complete
-Construction of borehole chamber done
-Construction of steel elevated tank complete
-Pump installation done
-Tower and solar panels installed
-Fencing not done

5,111,705.00Complete and operational
35.Kapteldon-Construction of pump house complete
-Construction of borehole chamber done
-Construction of steel elevated tank done
-Pump installation not yet done
-Pipeline to tank not yet laid
0On-going
36.Lower Kapchumba borehole water project-Construction of pump house completed
-Construction of borehole chamber done
-Construction of steel elevated tank completed
-Pump installation done
-Fencing not done
-Communal water point done
-Installation of tower and solar panels done
4,941,064.80Complete and Operating
37.Mafuta borehole water project-Construction of pump house completed
-Construction of borehole chamber done
-Construction of steel elevated tank completed
-Pump installation done
-Fencing not done
-Communal water point done
-Installation of tower and solar panels done
4,941,064.80Complete and Operating
38.Natuana borehole water project-Construction of pump house completed
-Construction of borehole chamber done
-Construction of steel elevated tank completed
-Pump installation done
-Fencing not done
-Communal water point done
-Installation of tower and solar panels done
4,941,064.80Complete and Operating
39.Kimurgoi borehole water project-Construction of pump house completed
-Construction of borehole chamber done
-Construction of steel elevated tank completed
-Pump installation done
-Fencing not done
-Communal water point done
-Installation of tower and solar panels done
4,941,064.80Complete and Operating
40.Kabenes borehole ECD water project-Construction of pump house completed
-Construction of borehole chamber done
-Construction of steel elevated tank completed
-Pump installation done
-Fencing not done
-Communal water point done
-Installation of tower and solar panels done
4,941,064.80Complete and Operating
41.Kewato borehole water project-Construction of pump house completed
-Construction of borehole chamber done
-Construction of steel elevated tank completed
-Pump installation done
-Fencing not done
-Communal water point done
-Installation of tower and solar panels done
4,941,064.80Complete and Operating
42.Nukiat borehole water project-Construction of pump house completed
-Construction of borehole chamber done
-Construction of steel elevated tank completed
-Pump installation done
-Fencing not done
-Communal water point done
-Installation of tower and solar panels done
4,941,064.80Complete and Operating
43.Toloita
-Construction of pump house completed
-Construction of borehole chamber done
-Construction of steel elevated tank completed
-Pump installation done
-Fencing not done
-Communal water point done
-Installation of tower and solar panels done
4,941,064.80-Complete and Operating

-Construction of steel elevated tank done at Jua kali since there was an existing tank at Toloita

 

  1. Water and Sanitation Master Plans developed.
  2. 81 borehole drilled.
  3. Elgarini Water project constructed.
  4. 15 water pans desilted.
  5. 225 community water projects developed and/or rehabilitated.
  6. Purchase of 125 skip containers and 6 refuse trucks for garbage collection.
  7. Distribution of 700,000 tree seedling to public schools.
  8. Installed security lights in the following peri-urban centres
    • Moi’s Bridge
    • Turbo
    • Burnt Forest
  9. Beautification of Nandi Park.
  10. Acquired a 20 acre dumpsite at Lorwa.
 

Chief Officer Department of Environment, Energy, Water & Natural Resources,
P.O.Box 40-30100, Eldoret,Kenya,
Tel; 053 2016000/ 2016603,
Email: environment@uasingishu.go.ke

F
F
Twitter
UGC_TheChampion on Twitter
Latest Tweet: @UGC_TheChampion hosts Kenya's only recruits training school. https://t.co/3GqE6E4Zc3
7,151 people follow UGC_TheChampion
Twitter Pic Foke_Len Twitter Pic MarkMuta Twitter Pic Kingmsaw Twitter Pic KeterZac Twitter Pic Edrabuog Twitter Pic CherianL Twitter Pic frank_fr Twitter Pic PeterRat
F